Working with a Traffic Management Crew: What to Expect on the Day

Short answer

Have access sorted, a named site contact and an approved plan. On the day, our crew sets up before you start, the STMS runs the traffic management while your team runs the work, and anything that affects the road goes through the STMS. When you're done, we take it all down and reopen the road.

Before the day

  • An approved plan. The crew can only set up to a plan the road controlling authority has approved, and it has to match the work you're doing.
  • A site contact. Someone on site who can make decisions about the work, with their mobile number.
  • Access. Room for our vehicles to reach the site and park where the plan shows.
  • Your start time. So we can have the site set up before your team starts.
  • Permit conditions. Anything you've been told about working hours or when the road must be open.

No plan yet? See getting a TMP approved.

Arrival and setup

The crew arrives before your start time. The STMS checks the site against the plan, briefs the crew and finds your site contact to confirm the work area.

Signs and cones go out in the order the plan sets, usually starting with the warning signs furthest from the work.

Wait for the STMS to say the site's ready before your team starts in the road.

Who runs what

  • The STMS runs the traffic management. Signs, cones, barriers, traffic controllers, and how traffic and people get past the site.
  • Your site manager runs your work. Your crew, your plant and the job itself, inside the area the plan sets aside.

Need to bring vehicles in or out? Check with the STMS first so traffic can be held. Working outside that area needs a revised plan (see below).

If the STMS sees something unsafe around the traffic management, they can stop it until it's safe. See What is an STMS?.

If things change

  • Within the plan. The plan needs to match the work, so it's worth getting it right up front. On the day, the STMS can only make minor changes within it.
  • Outside the plan. A longer closure, a different lane or extra hours need a revised plan, approved by the road controlling authority, from whoever designed it. If that's MW Training & Planning, they'll sort it.
  • On the road. Weather, heavy traffic or a nearby incident can mean the STMS makes minor adjustments within the plan, or pauses work until it's safe.

Finishing early or running late? Tell the STMS as soon as you know. Working outside your permitted hours usually needs the road controlling authority's approval.

Pack down

When you're finished, tell the STMS and get your crew, plant and materials clear of the road. The crew takes the traffic management down, usually in reverse order, and the road reopens. The STMS checks the road is clear before the crew leaves.

On multi-day jobs, the site may stay set up overnight or be packed down and set up again each day, depending on the plan.